MGMT 410
Production Management
Homework #10
Name:__________________________
APU Student ID.: __________________
Submission: Please upload your documents in the Assignment section on Canvas. You may either scan your homework documents or take pictures of them.
Grading Policy: Please show all your work on your paper. If you do not specify appropriate procedures on your homework, you will not get full credit.
Coverage of HW:
Chapter 14. Materials Requirement Planning (MRP)
[20 pts] Lot Sizing in Material Requirement System (MRP)
Michael Jordan, senior in the department of management at JSU, recently got a job as a production planner at Honda Plant in Lincoln, Alabama. His first task on the job training is to review the master production plan shown below: (Initial inventory = 140 units, Ordering cost = $300 per order, Lead time = 1 week, Holding cost = $2 per unit per week. No penalty cost for shortage/stock-outs.)
Develop an ordering plan and costs for this plant using the following techniques.
(a) Develop the lot-for-lot MRP table and calculate the total relevant costs.
Holding Cost = Ordering Cost = Total Cost =
(b) Develop the Economic Order Quantity (EOQ) lot sizing technique. (Assume EOQ = 200)
Holding Cost = Ordering Cost = Total Cost =
(c) Develop the Periodic Order Quantity (POQ) lot sizing technique. (Assume POQ Interval = 2 weeks)
Holding Cost = Ordering Cost = Total Cost =
(d) Among the three lot sizing techniques above, which one is the best strategy with the lowest cost?
2.
3.
4.
1
The post MGMT 410 Production Management Homework #10 Name:__________________________ APU Student ID.: __________________ Submission: appeared first on PapersSpot.