Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.
Baseline
Activity Name |
Start
(Baseline) |
Finish
(Baseline) |
Cost
(Baseline) |
Product | 6/2/14 | 5/25/15 | |
Requirements | 6/2/14 | 8/22/14 | 60,000.00 |
Design | 8/25/14 | 11/14/14 | 90,000.00 |
Build | 11/17/14 | 3/20/15 | 120,000.00 |
Test | 3/23/15 | 5/22/15 | 50,000.00 |
Release | 5/25/15 | 5/25/15 | 0.00 |
You have to report project status as of January 30, 2015. The associated schedule and cost information is provided below. Assume: (1) a five-day work week; and (2) a constant resource loading (i.e., the rate of planned expenditures is constant over the duration of each activity).
Actual
Activity Name | % Complete |
Start
(Actual) |
Finish
(Actual) |
Cost
(Actual) |
Product | 6/2/14 | NA | ||
Requirements | 100 | 6/2/14 | 8/30/14 | 68,000 |
Design | 100 | 8/31/14 | 11/20/14 | 85,000 |
Build | 70 | 11/21/14 | NA | 110,000 |
Test | 0 | NA | NA | 0 |
Release | 0 | NA | NA | 0 |
Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.
- Earned Value Measures
- Calculate earned value measures for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
Requirements | 68,000 | ||
Design | 85,000 | ||
Build | 110,000 | ||
Test | 0 | ||
Release | 0 | ||
Entire Project |
- What is the Budget at Completion (BAC) for the project?
- Earned Value Performance Measures
- Calculate earned value performance parameters for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity | Schedule Variance (SV) | Schedule Performance Index (SPI) | Cost Variance (CV) | Cost Performance Index (CPI) |
Requirements | ||||
Design | ||||
Build | ||||
Test | ||||
Release | ||||
Entire Project |
- Is the project ahead of schedule, on schedule, or behind schedule? Why?
- Is the project over budget, under budget, or on budget? Why?
- Earned Value Forecasts
- Assuming the Cost Performance Index (CPI) remains constant for the remainder of the project:
- What is the Estimate at Completion (EAC)?
- What is the Estimate-to-Complete (ETC)?
- Assuming the Cost Performance Index (CPI) remains constant for the remainder of the project:
- How much more or less money (other than the current budgeted amount) will you need to finish the project?
- How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget?
The post How much would the Cost Performance Index (CPI) have to change in order to complete the project within the original budget? appeared first on Best Custom Essay Writing Services | EssayBureau.com.