Homework Help Question & Answers
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic…
Given the following activity list and times in days: (15 points)
Activity Optimistic Most Likely Pessimistic
Time Time Time
A 7 10 12
B 6 8 14
C 5 9 12
D 12 14 21
E 10 12 15
F 4 5 8
G 1 3 8
H 12 15 17
NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”.
- Calculate the schedule duration of the critical path in days.
- What is the probability of the project being completed in 39 days?
- If you want a probability that the project will finish with no less that 85% certainty what is the project duration for that certainty? (5 points)
Note no interpolation is necessary from the table of Z values attached.